Notice for High Ridge Road Paving

The State just held the pre-construction meeting for the first phase of the High Ridge Road Paving which will be from Interlaken Road north to the State Line. The press release can be found here.

The milling and paving will be done at night, 8pm – 5am.

Milling: May 10 – May 21

Paving: May 23 – June 4

The state will be putting VMS boards out on Monday for advance notification.